Resource Progress Report

When run for a project, the Resource Progress report provides an overview of the current and future tasks assigned to everyone on a particular project. A Gantt-like view presents the person's name. task names, and Planned and Actual task start and end dates with % complete progress indicated on the Actual bar. An overview of the task information is provided by clicking on the plus sign beside each task name.

This report does not show Parent Tasks.

The time scale for this report is dynamically determined based on the duration of the tasks included in the report.

Note: A similar report is available for all tasks from all projects assigned to a resource.

 

How to run the Resource Progress Report for a project

  1. Right-click on the project you wish to run the report for.

  2. Select Resource Progress Report from the pop-up menu.

  3. The report will open in a new window.