The Export to CSV (comma-separated
values) function exports the latest information relating to Projects,
driven from the most recent
Management Report for each
Project.
Right click on any
personal workspace, and select Enterprise
Project Portfolio Reports. This option is also found
on any
user menu or
project menu.
You will be presented with the Project Picker. This function allows you to select a group of projects for inclusion in the report. For more information about the Project Picker click here.
In Step 5, select Export to csv.
In Step 6, click the Submit button.
You will be prompted to Open the file or Save the file to disk.
Note: all of the information in this report comes from the project's
most recent
Management Report. All times are reported
in GMT.
objid = Database Object Identifier
objname = Name of Database Object
effective_date = The date the last Management Report was published.
accomplishments = Accomplishments as outlined in last Management Report
upcoming = Upcoming as outlined in last Management Report
issues = Issues as outlined in last Management Report
risks = Risks as outlined in last Management Report
creator_id = Project Creator Database Object Identifier
creator_name = Name of Person who created the Project
proj_id = Project Database Object Identifier
proj_name = Name of Project
proj_executive_summary = Executive Summary from last Management Report
proj_charter = The published sections of the Project Charter
proj_number = Project Number from Project Information
proj_timezone_offset = Project Timezone Offset in minutes (if Project created using International version)
proj_timezone = Project Timezone (if Project created using International version)
proj_planned_startdate = Planned Start Date of the Project
proj_planned_enddate = Planned End Date of the Project
proj_planned_duration = Planned Duration of the Project
proj_baseline_planned_enddate_GMT = Baseline Planned End Date of the Project
proj_hoursworked = Hours Worked as entered on Project Information
proj_risk = Project Risk as entered on Project Information
proj_type = Project Type as entered on Project Information
proj_priority = Project Priority as entered on Project Information
proj_state = Project State as entered on Project Information
customer_id = Customer Database Object Identifier
customer_company_name = Company Name of Customer
customer_fname = Customer's First Name
customer_lname = Customer's Last Name
proj_effort = Project Effort as entered in Project Info
proj_id_number = Project ID Number as entered in Project Info
proj_reported_percent_complete = % Complete as entered in Project Info
proj_actual_enddate = Actual Project End Date as entered in Project Info
curr_phase_name = Name of Current Phase
curr_phase_comments = Comments applied to the Current Phase
curr_phase_startdate = Start Date of Current Phase
curr_phase_enddate = End Date of Current Phase
curr_phase_percent_complete = Percent Complete of Current Phase
curr_phase_gate = Gate of Current Phase
curr_phase_number = Number of Current Phase
stats_tasks_percent_complete = Weighted Percent Complete based on Estimated Hours
progress_salaried_employee = Salaried Employee Progress indicator - reported task progress (% Complete) versus amount of time charged to tasks
pse_ratio = Salaried Employees Ratio of time charged versus time expected
pse_hrs_charged = Salaried Employees Time charged to tasks
pse_hrs_expected = Salaried Employees Expected time charged based on Percent Complete and Estimated Time for Tasks
progress_internal_consultant = Internal Consultant Progress indicator - reported task progress (% Complete) versus amount of time charged to tasks
pic_ratio = Internal Consultant Ratio of time charged versus time expected
pic_hrs_charged = Internal Consultant Time charged to tasks
pic_hrs_expected = Internal Consultant Expected time charged based on Percent Complete and Estimated Time for Tasks
progress_external_consultant = External Consultant Progress indicator - reported task progress (% Complete) versus amount of time charged to tasks
pec_ratio = External Consultant Ratio of time charged versus time expected
pec_hrs_charged = External Consultant Time charged to tasks
pec_hrs_expected = External Consultant Expected time charged based on Percent Complete and Estimated Time for Tasks
budget_total_indicator = Green = Expenses + Capital < Budget, Yellow = Expense + Capital < (Budget * 1.1), Red if Expenses + Capital > (Budget * 1.1)
budget_total_planned = Total Planned Costs for Project
budget_total_cost = Total Actual Costs for Project
budget_total_budget = Total Budget for Project
budget_total_threshold = Total Budget * 1.1
budget_capital_indicator = Green = Capital < Budget, Yellow = Capital < (Budget * 1.1), Red if Capitla > (Budget * 1.1)
budget_capital_planned = Anticipated Costs for Capital items in Budget
budget_capital_cost = Capital items spent in the Budget
budget_capital_budget = Total Capital items in Budget
budget_capital_threshold = Budget Capital * 1.1
budget_expense_indicator = Green = Expenses < Budget, Yellow = Expense < (Budget * 1.1), Red if Expenses > (Budget * 1.1)
budget_expense_planned = Anticipated Costs for Expense items in Budget
budget_expense_cost = Expense items spent in the Budget
budget_expense_budget = Total Expense items on Budget
budget_expense_threshold = Budget Expenses * 1.1
cost_hr_expected_total = Total Hourly Costs all Assigned Members
cost_hr_expected_salaried = Total Hourly Costs all Salaried Employees who are Assigned Members
cost_hr_expected_internal_consultant = Total Hourly Costs all Internal Consultants who are Assigned Members
cost_hr_expected_external_consultant = Total Hourly Costs all External Consultants who are Assigned Members
cost_hr_variable_total = Total Variable Cost (Hourly Rate) to Project from Roster Information
cost_hr_variable_salaried = Variable Cost (Hourly Rate) to Project for Salaried Employees from Roster Information
cost_hr_variable_internal_consultant = Variable Cost (Hourly Rate) to Project for Internal Consultants from Roster Information
cost_hr_variable_external_consultant = Variable Cost (Hourly Rate) to Project for External Consultants from Roster Information
cost_hr_fixed_total = Total Fixed Cost to Project from Roster Information
cost_hr_fixed_salaried = Fixed Cost to Project for Salaried Employees from Roster Information
cost_hr_fixed_internal_consultant = Fixed Cost to Project for Internal Consultants from Roster Information
cost_hr_fixed_external_consultant = Fixed Cost to Project for External Consultants from Roster Information
cost_costsheet_planned_expense = Total of all items designated as Planned and Expense
cost_costsheet_actual_expense = Total of all items designated as Actual and Expense
cost_costsheet_planned_capital = Total of all items designated as Planned and Capital
cost_costsheet_actual_capital = Total of all items designated as Actual and Capital
benefit_y0 = Benefits to be accrued this year
benefit_y1 = Benefits to be accrued next year
benefit_y2 = Benefits to be accrued in year 3
benefit_y3 = Benefits to be accrued in year 4
benefit_y4 = Benefits to be accrued in year 5
benefit_total = Total Benefits to be accrued in Years 1-5
benefit_actualtodate = Actual Benefits recorded to date
benefit_stretchtarget = Dollar Value assigned in Benefits Report
roster_managers = Roster Members assigned as Managers of the Project
roster_participants = Roster Memebers assigned as Participants of the Project
roster_observers = Roster Members assigned as Observers of the Project